Hardhat Construction Company has a contract to construct a $4,500,000 bridge at an estimated cost of...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Hardhat Construction Company has a contract to construct a $4,500,000 bridge at an estimated cost of $4,000,000. The contract is to start in July 2014, and the bridge is to be completed in October 2016. The following data pertain to the construction period. 2014 2015 2016 Costs to date $4,050,000 Estimated costs to complete Progress billings during the year Cash collected during the year $1,000,000 3,000,000 900,000 750,000 $2,916,000 1,134,000 2,400,000 1,750,000 1,200,000 2,000,000 Record the journal entries for 2014, 2015, and 2016 using the percentage of completion method Record the income statement and balance sheet for 2014, 2015, and 2016 Hardhat Construction Company has a contract to construct a $4,500,000 bridge at an estimated cost of $4,000,000. The contract is to start in July 2014, and the bridge is to be completed in October 2016. The following data pertain to the construction period. 2014 2015 2016 Costs to date $4,050,000 Estimated costs to complete Progress billings during the year Cash collected during the year $1,000,000 3,000,000 900,000 750,000 $2,916,000 1,134,000 2,400,000 1,750,000 1,200,000 2,000,000 Record the journal entries for 2014, 2015, and 2016 using the percentage of completion method Record the income statement and balance sheet for 2014, 2015, and 2016
Expert Answer:
Answer rating: 100% (QA)
Contract price 4500000 4500000 4500000 Less estimated cost 100... View the full answer
Posted Date:
Students also viewed these accounting questions
-
Black Sea Construction Company has a contract to construct a $6,000,000 oil rig at an estimated cost of $5,300,000. The contract is to start in July 2017, and the oil rig is to be completed in...
-
A contractor has a contract to construct the sanitary sewer, water line, storm drain, and street lighting for a new subdivision. The contractor uses the cost codes in Figure 2-6. The original...
-
A chemical company has a contract to supply annually 3600 tonnes of product A at 24 a tonne and 4000 tonnes of product B at 14.50 a tonne. The basic components for these products are obtained from a...
-
What levels of visibility may be assigned to an attribute or an operation?
-
A sample of 25 production employees has been tested twice on a standard test of manual dexterity. The average change in the time required to finish the test was a decrease of 1.5 minutes, with a...
-
Define the following: a. Misstatement b. Population c. Tolerable misstatement d. Test of Details (TD) risk
-
Why is leasing versus buying an unfair comparison?
-
Given the comments in the case, do you surmise that the reason for the audit was to improve future projects or to ascertain the reasons for not meeting the projects goals, and if the latter, its...
-
Fluorine Limited (FL), a manufacturer of ships, has entered into the following contracts during the year ended 31 December 2022: (i) On 1 January 2022, FL entered into a contract with Alpha Limited...
-
Wilhelmina is a trader whose financial year ends on 31 March. Her trial balance at 31 March 2004 was as follows. Further information 1. Stock at 31 March 2004 cost $16.000. 2. The loan was received...
-
The remaining balance on a 30-year, $100,000 Fixed-rate mortgage loan financed at 8 percent after the 180th payment is (no calculation necessary) a. $100,000 b. $50,000 c. $76,782 d. $23,219
-
[1] Write the Boolean expression for the following logic circuits: D [2] Draw the logic circuit of the Boolean expression: X = A + B[C+D(B+C)] [3] Construct a truth table for the Boolean expression:...
-
The logging and monitoring of security events are two elements of a single process that is critical to the upkeep of safe infrastructure. Every action in your environment is a security event, from...
-
You have recently been placed in charge of refreshing the network and laptop equipment for your organization. The organization consists of 150 different employees who are located in each of the 48...
-
On December 31, 2020, Bridgeport Company borrowed $69,348 from Paris Bank, signing a 5-year, $106,700 zero-interest-bearing note. The note was issued to yield 9% interest. Unfortunately, during 2022,...
-
"Change or die!" is thus the rallying cry among today's... "Change or die!" is thus the rallying cry among today's managers worldwide and the changing nature of the workforce. Question 1 a. Discuss...
-
Using Varignon's Theorem, calculate the moment that the 250-N force creates about Point O. State the moment's magnitude and direction (Clockwise or Counterclockwise).
-
Let (x) = x 2 - 9, g(x) = 2x, and h(x) = x - 3. Find each of the following. (((--) 2
-
What minimum information must be extracted from a video clip of a moving object in order to quantify the object's motion?
-
The sequence in Figure P2.2 represents a ball rolling into a wall and bouncing off of it. The ball is \(10 \mathrm{~mm}\) in diameter. Make a graph showing the distance from the leading edge of the...
-
The sequence in Figure P2.3 represents a ball that is initially held above the ground. In the first frame the ball is released. In subsequent frames the ball falls, bounces on the ground, rises, and...
Study smarter with the SolutionInn App