Question: HAULING & TRANSPORTING MATERIALS A contractor will use a 1 - cy loader, with 6 5 c y h r . production rate, to move

HAULING & TRANSPORTING MATERIALS
A contractor will use a 1-cy loader, with 65cyhr. production rate, to move 53,000
cy of aggregates to the construction site. Diesel dump trucks, with 12-cy capacity,
will be used to haul the material a distance of 18 miles from the quarry to the
construction site at an average speed of 40 mph loaded (hauling) and 55 mph when
returning. The estimated time to dump a load is 5 minutes. In addition to the time
required to load a truck, there will be an average of 3 minutes waiting by a truck
before moving into position for loading. Assume a 50-min-hour time factor for
both the loader and the trucks.
Given the following unit costs, calculate the cost per cubic yard to move the total
volume of aggregates to the construction site, after balancing the number of trucks
to the loader production?
HAULING & TRANSPORTING MATERIALS A contractor

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!