Question: he critical path(s) for the network activities shown below is(are) ________ with duration ________. Activity Duration Immediate Predecessors A 4 --- B 3 A C

he critical path(s) for the network activities shown below is(are) ________ with duration ________.

Activity Duration Immediate
Predecessors
A 4 ---
B 3 A
C 7 --
D 5 A
E 5 B,C,D