A company is designing a product layout for a new product. They plan to use this production
Fantastic news! We've Found the answer you've been seeking!
Question:
A company is designing a product layout for a new product. They plan to use this production line 16 hours a day in order to meet forecasted demand of 1200 units per day. For output to equal forecasted demand, what should be the actual cycle time for this production?