Question: help fast Question 8 1 pts The process design team at a manufacturer has broken an assembly process into eight basic tasks, each with a
help fast
Question 8 1 pts The process design team at a manufacturer has broken an assembly process into eight basic tasks, each with a required time and predecessor as shown in the table. They work 7 hours a day and want to produce at a rate of 360 units per day. Task Time (sec) Predecessor A A 40 B 35 A A 30 -- D 40 B.C E 25 D F 50 D G G 20 E E I 30 F G Total 270 (sed) Assign eligible tasks without exceeding the required cycle time. If there is a tie (two or more eligible tasks wouldn't exceed the required cycle time), assign the largest eligible task first. What task/tasks should be assigned to the first workstation (start of the process)? O AE , AC
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
