Question: help!! thanks! // operations mgmt pter 08 Homework: Facility and Work Design A small assembly line for the assembly of power steering pumps needs to
pter 08 Homework: Facility and Work Design A small assembly line for the assembly of power steering pumps needs to be balanced. Precedence diagram is shown below. The cycle time is determined to be 2.2 minutes. How would the line be balanced by choosing the assignable task having the langest task time first? fill in the table below. If your answer is zero, enter " 0 ". Round your answers to one decimal place. What is the assembly -line efficency? Round your answer to one decimal place