Question: here are three activities under Activity A. A1: 5 days A2: 4 days A3: 10 days A1 is the predecessor of both A2 and A3.
here are three activities under Activity A. A1: 5 days A2: 4 days A3: 10 days A1 is the predecessor of both A2 and A3. All the dependencies are Finish-to-Finish. A1 starts on 6/6/2022. When can we finish A3? A. We cannot finish A3 because it does not have any dependencies with A2. B. 6/30/2022 C. 6/17/2022 D. 6/24/2022