Question: There are three activities under Activity A. A1: 5 days A2: 4 days A3: 10 days A1 is the predecessor of both A2 and A3.

There are three activities under Activity A.

A1: 5 days

A2: 4 days

A3: 10 days

A1 is the predecessor of both A2 and A3. All the dependencies are Finish-to-Finish.

A1 starts on 6/6/2022.

When can we finish A3?