Question: Here is some data for Project ABC Budget $ 5,398 thousand Start Workday Finish Workday Reporting Day Earned Value $ 262 thousand Planned Value $

Here is some data for Project "ABC" Budget $ 5,398 thousand Start Workday Finish Workday Reporting Day Earned Value $ 262 thousand Planned Value $ 464 thousand Actual Cost $ 671 thousand Using a "Do-Nothing Forecast" predict the estimated finishing Workday when you expect the project will be completed (given that the project started on time)? If the project will be completed partway through a Workday, round UP to the next integer value. The allowed error margin is + 2 Workdays, with no deduction of marks