Question: Here is some data for Project XYZ $ 5,869 thousand 15 Budget Start Workday Finish Workday Reporting Day 113 38 Earned Value $ 246 thousand

Here is some data for Project "XYZ" $ 5,869

Here is some data for Project "XYZ" $ 5,869 thousand 15 Budget Start Workday Finish Workday Reporting Day 113 38 Earned Value $ 246 thousand Planned Value $ 386 thousand Actual Cost $ 858 thousand Using a "Do-Nothing" forecast, estimate the extra amount of money that will need to be added to (or subtracted from) the budget, in thousands of dollars, rounded to the nearest integer number of thousands. The allowed error margin is 2% or 1 thousand dollars, whichever is larger