Question: Here is the information about the project: Activity Immediate Predecessors Optimistic Time Most Likely Time Pessimistic Time A N / A 2 3 4 B

Here is the information about the project:
Activity Immediate Predecessors Optimistic Time Most Likely Time Pessimistic Time
A N/A 234
B A 125
C B 123
D A 123
E B 456
F B, C, D 246
G F 226
Answer Q8 to Q10 according to this information. Use 2 decimal points in the calculation.
Q8. The mean activity time for activity F is 0.67
Group of answer choices
True
False
Flag question: Question 9
Question 91 pts
Make sure the Earliest Starting Time of activity F is 7.33. The mean of the Total Project Completion Time is 14 and the standard deviation is around 1.25.
Group of answer choices
True
False
Flag question: Question 10
Question 101 pts
Which of the following statement is not true?
Group of answer choices
The 85% confidence interval is between 12.20 and 15.80 if we round the numbers to 2 decimal points.
The probability that the project will be longer than 12 days is more than 90%.
If we want to be sure (90% sure) that the project will be completed by the day we promised. We should promise 14 days.
The probability the project will be shorter than 8 days is almost impossible.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!