Question: Here is the information about the project: Activity Immediate Predecessors Optimistic Time Most Likely Time Pessimistic Time A N / A 2 3 4 B
Here is the information about the project:
Activity Immediate Predecessors Optimistic Time Most Likely Time Pessimistic Time
A NA
B A
C B
D A
E B
F B C D
G F
Answer Q to Q according to this information. Use decimal points in the calculation.
Q The mean activity time for activity F is
Group of answer choices
True
False
Flag question: Question
Question pts
Make sure the Earliest Starting Time of activity F is The mean of the Total Project Completion Time is and the standard deviation is around
Group of answer choices
True
False
Flag question: Question
Question pts
Which of the following statement is not true?
Group of answer choices
The confidence interval is between and if we round the numbers to decimal points.
The probability that the project will be longer than days is more than
If we want to be sure sure that the project will be completed by the day we promised. We should promise days.
The probability the project will be shorter than days is almost impossible.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
