Question: heres a better image for the problem Activity A 7911 B 123 789 D 2511 E 234 F 148 G 678 H 269 Please answer

Activity A 7911 B 123 789 D 2511 E 234 F 148 G 678 H 269 Please answer the following questions. 1. Compute (expectation), (standard deviation) and (variance) of the duration of each activity. (Note: Keep one decimal place after the dot in your result.) Activity Expected Standard Variance of deviation duration duration A B D E F G H 2. Identify the critical path by visual inspection. (Hint: there are total 4 paths from start to end.) The critical path(s) is: 3. Compute (expectation) and (variance) of the duration of the project. (Note: keep one decimal place after the dot in your result.) 4. What's the probability that the project is completed within 23 days. 5. For what project due date (denoted as Ts) is the project to be completed on time with 95% chance? B D E End H The following table shows a, m, b (in days) for each activity of the project. a 2 The following table shows a, m, b (in days) for each activity of the project. Activity m b A 7 9 11 B 1 2 3 8 2 5 11 2 3 4 F 1 4 8 G 6 7 8 H 2 6 9 Please answer the following questions. 7 9 D E 1. Compute te (expectation), o (standard deviation) and V (variance) of the duration of each activity. (Note: Keep one decimal place after the dot in your result.) Activity Expected Standard Variance of duration to deviation o duration V A B D E F G H
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts