Question: Use PERT Technique to calculate 1 ) Given the immediate predecessors and a , m , b for each activity in the tables below, compute:

Use PERT Technique to calculate
1) Given the immediate predecessors and a, m, b for each activity in the tables below, compute:
a) te and V for each activity
b) Te and Vp for the project.
c) What is P (Te <23)?
d) What is P (Te <32)?
e) For what Ts is the probability 95 percent that the project will be completed?
f) For what Ts is the probability 85 percent that the project will be completed?
Activity Predecessors a m b
A 7911
B A 123
C A 789
D B 2511
E C 234
F C 148
G D, E 678
H F, E 269