Question: Use PERT Technique to calculate 1 ) Given the immediate predecessors and a , m , b for each activity in the tables below, compute:
Use PERT Technique to calculate
Given the immediate predecessors and a m b for each activity in the tables below, compute:
a te and V for each activity
b Te and Vp for the project.
c What is P Te
d What is P Te
e For what Ts is the probability percent that the project will be completed?
f For what Ts is the probability percent that the project will be completed?
Activity Predecessors a m b
A
B A
C A
D B
E C
F C
G D E
H F E
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
