Question: Heuristics is used in resource allocation for the resource-constrained projects. What is the second priority rule that is used in the parallel method to apply

Heuristics is used in resource allocation for the
Heuristics is used in resource allocation for the
Heuristics is used in resource allocation for the
Heuristics is used in resource allocation for the
Heuristics is used in resource allocation for the resource-constrained projects. What is the second priority rule that is used in the parallel method to apply the heuristics? Select one: a. Smallest duration b. Highest ID number c. Lowest ID number d. Maximum slack e. Longest duration Resource allocation methods are different for constrained projects and _ _constrained projects. Select one: A. Time, quality B. Quality, resource o C. Cost, time D. Quality, cost E. Time, resource Alicia has realized that two activities in her project cannot be done at the same time because not enough resources are available. Activity 5 is critical and has a duration of 6 days. Activity 4 has 3 days of slack and a duration of 3 days. What does Alicia should do? Select one: A. Select Activity 4 first B. Select Activity 5 first C. Pick either one of the two activities D. Consult with his direct manager E. Consult with his project team members Which of the following is correct statement? Select one: A. A risk response is established only for moderate risks while contingency plans are established for major risks. B. A risk response is part of the actual implementation plan and action is taken before the risk can materialize, while a contingency plan goes into effect only after the risk has transpired. C. A risk response is only effective when you are able to assess the likelihood of the risk and its impact on the project; all other risks are covered by contingency planning. D. A risk response is created by the project team and the project manager while the project manager and the customer agree on the contingency plan. E. A risk response is action that is the response to a risk once it has happened and the contingency plan is created by the customer if the risk response fails

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!