Question: hg Enabled: Midterm 2 Compute the takt time for a system where the total time per shift is 4 1 0 minutes, there is one

hg Enabled: Midterm 2
Compute the takt time for a system where the total time per shift is 410 minutes, there is one shift, and workers are given 210-minute breaks and 35 minutes for lunch. Daily demand is 346 units. (Round your answer to 2 decimal places.)
Takt time