Question: Hint: p ( 0 < z < 1 . 6 4 5 ) = 0 . 4 5 Activity Immediate Predecessors Completion Time ( Weeks
Hint: p z
Activity
Immediate
Predecessors
Completion Time Weeks
Optimistic
Most Likely
Pessimistic
A
NA
B
A
C
A
D
A
E
B C
F
D
What is the confidence interval of the total project completion time?