Question: Activity Immediate Predecessors Completion Time ( Weeks ) Optimistic Most Likely Pessimistic A N / A 1 2 3 B A 2 4 6 C

Activity
Immediate
Predecessors
Completion Time (Weeks)
Optimistic
Most Likely
Pessimistic
A
N/A
1
2
3
B
A
2
4
6
C
A
2
5
8
D
A
1
1
1
E
B, C
2
3
4
F
D
1
2
3
What is the probability the project will be longer than 9.5 weeks?
Group of answer choices
0.6736
0.7054
0.1736
0.2054