Question: Historical Data to be used for this assignment: 21/4/2012 CONCRETE CREW 1 SET: 10 M3 CONCRETE 5 HRS 4/6/2013 CONCRETE CREW 1 SET: 4 M3

Historical Data to be used for this assignment: 21/4/2012 CONCRETE CREW 1 SET: 10 M3 CONCRETE 5 HRS 4/6/2013 CONCRETE CREW 1 SET: 4 M3 CONCRETE 2 HRS 15/7/2015 CONCRETE CREW 1 SET: 20 M3 CONCRETE 8 HRS 5/5/2016 CONCRETE CREW 1 SET: 18 M3 CONCRETE 6 HRS 7/10/2018 CONCRETE CREW 1 SET: 13 M3 CONCRETE 6 HRS 1. What is the average Productivity Rate for this crew? /3 points 2. Using data from question 1, how many work hours would an estimator QTO labour for the following projects at standard conditions: a. 22 m3 of concrete? b. 16 m3 of concrete? c. 34 m3 of concrete? d. 105 m3 of concrete? e. 1009 m3 of concrete? /5 points 3. Describe Productivity Factor. /2 points 4. Apply a productivity factor to the QTO estimates in question 2. In 2-A and 2-B apply a Productivity Factor of .86. In question 2-C, 2-D, and 2-E apply a productivity factor of 1.34. Explain if conditions were harsher or better than standard for each new QTO amount? /10 points Content: /20 EOP: /5 Total: /25

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!