Question: ho how would you solve this? Question 3 18.75 pts Job J is currently awaiting processing at WC202. I will require 6 hours of processing
ho
how would you solve this?
Question 3 18.75 pts Job J is currently awaiting processing at WC202. I will require 6 hours of processing time at WC202. After WC202, J will have process requirements of ... 13 hours at WC504 11 hours at WC603 9 hours at WC429 Standard move/queue time is calculated at 5 hours per work center. If Job J is due 92 hours from now, what is J's Slack per Remaining Operation? (Round to 2 decimal places)Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!