Question: Job J is currently awaiting processing at WC202. J will require 14 hours of processing time at WC202. After WC202, J will have process requirements

Job J is currently awaiting processing at WC202. J will require 14 hours of processing time at WC202. After WC202, J will have process requirements of ...

14 hours at WC504

7 hours at WC603

11 hours at WC429

Standard move/queue time is calculated at 4 hours per work center.

If Job J is due 52 hours from now, what is J's Critical Ratio? (Round to 2 decimal places)