Question: Homework 1 - Process Fundamentals Question 1 : ( 1 5 points ) A process flow diagram is as follows. In step 1 , the

Homework 1- Process Fundamentals
Question 1: (15 points)
A process flow diagram is as follows. In step 1, the two machines (M1 & M2)
A.(6 points) Suppose the starting times of M1 and M2 are staggered by 4
minutes, i.e., M1 starts at time 0 and M24 minutes later. Then new parts
are fed into M1 and M2 whenever they become available. Draw a Gantt
chart, and identify the cycle time and average manufacturing lead-time of
the whole process.
B.(2 points) What's the bottleneck?
C.(5 points) Calculate each machine's contribution to WIP and total WIP.
D.(2 point) Verify Little's law.
Question 2: (5 points)
The department of tax regulations of the IRS is in charge of writing tax
regulations in accordance with tax laws passed by the congress. The
department completes 720 projects per year, on average. It was reported by
the WSJ (Wall Street Journal) that the average number of projects "on their
plate" is 348. The department head claims that on average, the time to
complete a project is less than six months. Do you have any reason to disagree?
Explain why.
Question 3: (10 points)
A facility conducts three-day programs and operates 7 days per week. A new
batch of 400 starts a program on each day of the week except Saturday and
Sunday (A person joining on Monday will leave on Thursday; one joining on
Tuesday will leave on Friday and so on). Assume that January 1 is a Monday
and the facility is just opening after a long Christmas break.A facility products three day programs and operates 7 days per week. A new batch of 400 starts a program on each day of the week except saturday and sunday Question 2: (5 points)
The department of tax regulations of the IRS is in charge of writing tax
regulations in accordance with tax laws passed by the congress. The
department completes 720 projects per year, on average. It was reported by
the WSJ (Wall Street Journal) that the average number of projects "on their
plate" is 348. The department head claims that on average, the time to
complete a project is less than six months. Do you have any reason to disagree?
Explain why.
 Homework 1- Process Fundamentals Question 1: (15 points) A process flow

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!