Question: Homework Two 1 . ( 5 0 points ) The Widget Maker Company is bidding for a new job that requires building four widget prototypes.
Homework Two
points The Widget Maker Company is bidding for a new job that requires building
four widget prototypes. The company has never built the particular widget before, but
its experts believe that its designers and workers will be able to pick it up with a learning
rate of The activity of designing and building prototypes will gain from this
learning rate for at least five cycles. The proposal team has come up with the following
action plan and effort estimates for producing the four units.
S No Task Effort in hrs Precedence
Concept development
Design framework FS
Design and build first prototype FS
Ship to customer FS
Analyze feedback FS weeks lag
Design and build second prototype FS
Ship to customer FS
Analyze feedback FS weeks lag
Design and build third prototype FSFS
Ship to customer FS
Analyze feedback FSweeks lag
Design and build final prototype FSFS
Ship to customer FS
Update customer design knowledge base FSFS
The company plans its work assuming a efficiency of its staff members. Task Design
framework, and Task Update design knowledge base, require an expert designer who is
available only of the time due to other commitments.
The company has an average labor rate of $hour The benefit rate is Its overhead costs
are and its profit margin is The project plans are to be developed assuming hours
per working day and working days per week.
A Provide a table with estimated durations for each task taking efficiency and availability in
consideration where applicable. Please round to the nearest tenth of an hour. points
HINT: provide a table with a column for allocated hr efficiency and a column for total
task duration hr for each task.
B What is the total project duration in calendar weeks and completion date that the company
should propose? Assume a start date of Monday, February and that the company
believes its estimates already are generous and no additional time buffer is needed.
points
C What is the amount that the company should bid for this project? points
points Diagram of network is below
A
B
C
D
E
Activity Max Crash
days available
Normal Cost Total crash
cost assuming
max days
used
Crash
costday
A days $ $
B days $ $
C days $ $
D days $ $
E days $ $
Total normal cost
Provide the normal cost at days and crash costday values. Determine the critical path. If the
goal is to complete the project in days at the lowest cost, what tasks do you crash? What is
the new total cost?
Code: activity, time
resource units
A
D
H
B
E
F
C
G
I,
Provide the following using Excel or powerpoint may be helpful:
Gantt chart and resource loading chart for the project before leveling points
If the total number of resources available is which tasks can be moved
leveled to meet the limits
Gantt chart and resource loading chart for the project after leveling points
Comment on the effect of leveling points
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock