Question: Homework Two 1 . ( 5 0 points ) The Widget Maker Company is bidding for a new job that requires building four widget prototypes.

Homework Two
1.(50 points) The Widget Maker Company is bidding for a new job that requires building
four widget prototypes. The company has never built the particular widget before, but
its experts believe that its designers and workers will be able to pick it up with a learning
rate of 80%. The activity of designing and building prototypes will gain from this
learning rate for at least five cycles. The proposal team has come up with the following
action plan and effort estimates for producing the four units.
S. No. Task Effort in hrs Precedence
1 Concept development 36
2 Design framework 181FS
3 Design and build first prototype 722FS
4 Ship to customer 3.63FS
5 Analyze feedback 14.44FS+2 weeks lag
6 Design and build second prototype 57.63FS
7 Ship to customer 3.66FS
8 Analyze feedback 14.47FS+2 weeks lag
9 Design and build third prototype 50.65FS,6FS
10 Ship to customer 3.69FS
11 Analyze feedback 14.410FS+2weeks lag
12 Design and build final prototype 46.18FS,9FS
13 Ship to customer 3.612FS
14 Update customer design knowledge base 1811FS,13FS
The company plans its work assuming a 90% efficiency of its staff members. Task 2, Design
framework, and Task 14, Update design knowledge base, require an expert designer who is
available only 50% of the time due to other commitments.
The company has an average labor rate of $50/hour. The benefit rate is 30%. Its overhead costs
are 50% and its profit margin is 20%. The project plans are to be developed assuming 8 hours
per working day and 5 working days per week.
A. Provide a table with estimated durations for each task taking efficiency and availability in
consideration where applicable. Please round to the nearest tenth of an hour. (30 points)
HINT: provide a table with a column for allocated hr (efficiency) and a column for total
task duration hr for each task.
B. What is the total project duration in calendar weeks and completion date that the company
should propose? Assume a start date of Monday, 6 February 203, and that the company
believes its estimates already are generous and no additional time buffer is needed. (10
points)
C. What is the amount that the company should bid for this project? (10 points)
2.(30 points) Diagram of network is below
1
A
7
2
B
3
C
6
3
D
3
4
E
2
5
Activity Max Crash
days available
Normal Cost Total crash
cost assuming
max days
used
Crash
cost/day
A 7 days 3 $500 $300
B 3 days 1 $200 $150
C 6 days 2 $500 $400
D 3 days 2 $200 $300
E 2 days 1 $300 $250
Total normal cost =
Provide the normal cost at 12 days and crash cost/day values. Determine the critical path. If the
goal is to complete the project in 10 days at the lowest cost, what tasks do you crash? What is
the new total cost?
Code: activity, time
resource units
1
A,10
6
2
D,10
2
6
H,5
2
B,10
43
E,5
10
F,15
8
C,5
4
4 G,10
6
5
I, 5
2
7
3. Provide the following (using Excel or powerpoint may be helpful):
Gantt chart and resource loading chart for the project before leveling (20 points)
If the total number of resources available is 20, which tasks can be moved
(leveled) to meet the limits?
Gantt chart and resource loading chart for the project after leveling (20 points)
Comment on the effect of leveling (5 points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!