The Widget Maker Company is bidding for a new job that requires building four widget prototypes....
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
The Widget Maker Company is bidding for a new job that requires building four widget prototypes. The company has never built the particular widget before, but its experts believe that its designers and workers will be able to pick it up with a learning rate of 80%. The activity of designing and building prototypes will gain from this learning rate for at least five cycles. The proposal team has come up with the following action plan and effort estimates for producing the four units. S. No. Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Effort in hrs Precedence 36 18 Concept development Design framework Design and build first prototype Ship to customer Analyze feedback Design and build second prototype Ship to customer Analyze feedback Design and build third prototype Ship to customer Analyze feedback Design and build final prototype 46.1 Ship to customer 3.6 Update customer design knowledge base 18 72 3.6 14.4 57.6 3.6 14.4 50.6 3.6 14.4 1FS 2FS 3FS 4FS+2 weeks lag 3FS 6FS 7FS+2 weeks lag 5FS, 6FS 9FS 10FS+2weeks lag 8FS, 9FS 12FS 11FS, 13FS The company plans its work assuming a 90% efficiency of its staff members. Task 2, Design framework, and Task 14, Update design knowledge base, require an expert designer who is available only 50% of the time due to other commitments. The company has an average labor rate of $50/hour. The benefit rate is 30%. Its overhead costs are 50% and its profit margin is 20%. The project plans are to be developed assuming 8 hours per working day and 5 working days per week. A. Provide a table with estimated durations for each task taking efficiency and availability in consideration where applicable. Please round to the nearest tenth of an hour. (30 points) HINT: provide a table with a column for allocated hr (efficiency) and a column for total task duration hr for each task. B. What is the total project duration in calendar weeks and completion date that the company should propose? Assume a start date of Monday, 6 February 2023, and that the company believes its estimates already are generous and no additional time buffer is needed. (10 points) C. What is the amount that the company should bid for this project? (10 points) The Widget Maker Company is bidding for a new job that requires building four widget prototypes. The company has never built the particular widget before, but its experts believe that its designers and workers will be able to pick it up with a learning rate of 80%. The activity of designing and building prototypes will gain from this learning rate for at least five cycles. The proposal team has come up with the following action plan and effort estimates for producing the four units. S. No. Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Effort in hrs Precedence 36 18 Concept development Design framework Design and build first prototype Ship to customer Analyze feedback Design and build second prototype Ship to customer Analyze feedback Design and build third prototype Ship to customer Analyze feedback Design and build final prototype 46.1 Ship to customer 3.6 Update customer design knowledge base 18 72 3.6 14.4 57.6 3.6 14.4 50.6 3.6 14.4 1FS 2FS 3FS 4FS+2 weeks lag 3FS 6FS 7FS+2 weeks lag 5FS, 6FS 9FS 10FS+2weeks lag 8FS, 9FS 12FS 11FS, 13FS The company plans its work assuming a 90% efficiency of its staff members. Task 2, Design framework, and Task 14, Update design knowledge base, require an expert designer who is available only 50% of the time due to other commitments. The company has an average labor rate of $50/hour. The benefit rate is 30%. Its overhead costs are 50% and its profit margin is 20%. The project plans are to be developed assuming 8 hours per working day and 5 working days per week. A. Provide a table with estimated durations for each task taking efficiency and availability in consideration where applicable. Please round to the nearest tenth of an hour. (30 points) HINT: provide a table with a column for allocated hr (efficiency) and a column for total task duration hr for each task. B. What is the total project duration in calendar weeks and completion date that the company should propose? Assume a start date of Monday, 6 February 2023, and that the company believes its estimates already are generous and no additional time buffer is needed. (10 points) C. What is the amount that the company should bid for this project? (10 points)
Expert Answer:
Related Book For
Posted Date:
Students also viewed these general management questions
-
3 4 5 6 7 8 9 10 11 12 13 A 14 Cost of the Asset 15 Life of the Asset in Years 16 Book Value of the Asset after 5 years 17 Depreciable Basis 18 Yearly depreciation 19 After tax Salvage Value in year...
-
Year 1 2 3 4 5 6 7 A coal mining company is expanding its existing operation. The company expects that it will experience an increasing stripping ratio scenario in the expansion area, and with...
-
A 1 defects size B D E 88888888888888888888888888 2 21 3 24 4 16 5 12 6 15 7 5 8 28 9 20 10 31 11 25 12 20 13 24 14 16 15 19 16 10 17 17 18 13 19 22 20 18 21 39 22 30 23 24 24 16 25 19 26 17 27 15...
-
A solid conducting cylinder of radius 0.1 m and mass of 4 kg rests on horizontal conducting rails (Figure). The rails, separated by a distance a?= 0.4 m, have a rough surface so the cylinder rolls...
-
Explain why zoning laws, which allow certain land uses only in specific locations, might be justified in dealing with a problem of negative externalities. Explain why tax breaks to businesses that...
-
The difference of two numbers is 4 and their sum is 14. What is their product?
-
In 1997, Bernard Bilski and Rand Warsaw filed a patent application for a method of hedging risk in the field of commodities trading. In effect, the asserted invention was a method of protecting...
-
Pueblo Service is a fast-growing chain of oil-change stores. The following data are available for last years services: Pueblo Service performed 396,000 oil changes last year. It had budgeted 360,000...
-
(d) For the following Boolean expression, give: i. The truth table F(a, b, c, d) = ( + b.d).(c.b.a. + .d) ii. The Karnaugh map iii. The minimal sum of products expression
-
Build this interface with Java and give me the code Model Welcome to Model ads Welcome User Login Form UserName Password Passowd Get Username get Password 2022 Model
-
Describe how you could use social media (like LinkedIn) to make an existing professional contact more personal in nature while still maintaining your privacy.
-
Katherine acquired a 40-year lease on a property on 31 August 2003 for 75,000. On 31 August 2021 she assigned the lease to Francesco for 97,500. The property was never Katherine's residence. Compute...
-
Marta Tompkins, a graduate in industrial engineering from Purdue University, was excited. She had accepted a new job in South Carolina as the Operations & Logistics manager at Kempfer Furniture,...
-
Samantha bought a house for 47,500 on 1 August 2000 and occupied the house as her principal private residence. On 1 June 2002 she began to use one-fifth of the house for business purposes....
-
Saeed made the following purchases of ordinary shares in Hyban plc: In June 2017, the company made a 1 for 20 rights issue at 1.50 per share and Saeed took up the shares which he was offered....
-
What is vendor-managed inventory?
-
Assuming semiannual compounding, a 15-year zero coupon bond with a par value of $1,000 and a required return of 12.2% would have a price of _________.
-
If someone's Z-score for a variable was 0.67. Their score is a significant extreme score. Their score is not significant. O Their score is slightly above average. O Their score is an outlier.
-
People like to have a stable living standard from one year to the next. Yet studies show that the level of consumption drops suddenly, predictably, and significantly at retirement (contrary to Figure...
-
Consider a bond with a face value of $1000 and a coupon of $100. Suppose the interest rate is 10 percent. Does the PDV of the promised payments depend on the bond's maturity? Why or why not? Think...
-
Suppose a single monopolist controls the market for Coke and Pepsi in Worked-Out Problem 19.2. If the monopolist sets the same price for Coke and Pepsi, what price would maximize its profit? How does...
-
Use the magnitudes (Richter scale) of the earthquakes listed in Data Set 16 in Appendix B. In 1989, the San Francisco Bay Area was struck with an earthquake that measured 7.0 on the Richter scale....
-
James Madison, the fourth President of the United States, was 163 cm tall. His height converts to the z score of -2.28 when included among the heights of all presidents. Is his height above or below...
-
Carbon monoxide is measured in San Francisco on five different days, and the mean of those five values is 0.62 parts per million. Four of the values (in parts per million) are 0.3, 0.4, 1.1, and 0.7....
Study smarter with the SolutionInn App