Question: Homework3: Draw the network diagram by using AON technique for the following activities, define the located activities on the critical path, define the total project

Homework3: Draw the network diagram by using AON

Homework3: Draw the network diagram by using AON technique for the following activities, define the located activities on the critical path, define the total project duration, and find all of ES, EC, LS, LC, TF, and FF. Precedent Activity B D E F G H I J K L M N O P Q R S A, E, G A, E C, L, M, N A B, C, E, I, J, K, S A B, C, P B, C, H, O B, C, G, O B, C, E, I, Q F, H, I, J, K, R B, C, F, H, I, J, R Duration, Weeks 3 4 1 1 5 2 3 1 1 5 1 6 3 5 10 10 10 20 2 B, C, I, O

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!