Question: How do I find the new critical path and the new slack/float? Exercise 2 Project Planning a Vacation Activity A: Decide on vacation dates and
How do I find the new critical path and the new slack/float?
Exercise 2 Project Planning a Vacation
Activity A: Decide on vacation dates and location
Activity B: Buy airline tickets at least 21 days in advance of departure date
Activity C: Make hotel reservation
Activity D: Make car rental reservation
Activity E: Arrange for hold on mail delivery
Activity F: Arrange for hold on newspaper delivery
Activity G: Arrange for pets to be taken care of
Activity H: Pack for trip
Activity I: Depart
| Activity | Preceding Activities | Duration in days |
| A | Start | 8 |
| B | A | 4 |
| C | A | 10 |
| D | B, C | 2 |
| E | D | 2 |
| F | D | 2 |
| G | D | 3 |
| H | E, F, G | 2 |
| I | H | 1 |
If Activity E now takes four days instead of two days, has the critical path changed?
Based on the information in question 4, what is the new critical path and what is its duration?
Based on question number 4, what is the slack/float of the path with the longest (most) slack?