Question: How do I calculate the slack/flow Exercise 2 Project Planning a Vacation Activity A: Decide on vacation dates and location Activity B: Buy airline tickets

How do I calculate the slack/flow

Exercise 2 Project Planning a Vacation

Activity A: Decide on vacation dates and location

Activity B: Buy airline tickets at least 21 days in advance of departure date

Activity C: Make hotel reservation

Activity D: Make car rental reservation

Activity E: Arrange for hold on mail delivery

Activity F: Arrange for hold on newspaper delivery

Activity G: Arrange for pets to be taken care of

Activity H: Pack for trip

Activity I: Depart

Activity

Preceding Activities

Duration in days

A

Start

8

B

A

4

C

A

10

D

B, C

2

E

D

2

F

D

2

G

D

3

H

E, F, G

2

I

H

1

Which path is the critical path and what is its duration?

ACDGHI; 26 DAYS

What is the slack/float for Activity F?

What is the slack/float for Activity B?

If Activity E now takes four days instead of two days, has the critical path changed?

Based on the information in question 4, what is the new critical path and what is its duration?

Based on question number 4, what is the slack/float of the path with the longest (most) slack?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!