Question: How do project managers use prioritization to add value to their team? They give out tasks to those with the most seniority . They please

How do project managers use prioritization to add value to their team?
They give out tasks to those with the most seniority.
They please project sponsors by going under budget.
They determine which tasks are the most critical to the success of the project.