Question: How does a tracking Gantt chart help communicate project progress? The tracking Gantt chart graphically compares the plan and actual time performance. O The tracking

How does a tracking Gantt chart help communicate
How does a tracking Gantt chart help communicate project progress? The tracking Gantt chart graphically compares the plan and actual time performance. O The tracking Gantt chart graphically compares the plan and actual cost performance. The tracking Gantt chart graphically compares the plan and eamed value performance. The tracking Gantt chart graphically compares the plan and BAC performance