Question: How is the Critical Path determined in a project network diagram? Group of answer choices It is the path with the most dependencies. It is
How is the Critical Path determined in a project network diagram?
Group of answer choices
It is the path with the most dependencies.
It is the path with the highest resource allocation.
It is the path with the fewest tasks.
It is the path with zero slack or float.