Question: How much slack is there in task C? If the crash costs for each task are A-200, B-150, C-250, D-275, and E-200, you would crash

How much slack is there in task C?
If the crash costs for each task are A-200, B-150, C-250, D-275, and E-200, you would crash ___ if you were asked to shorten the project by one day. Simply enter the capitalized letter for the task.
You are given the following parameters for a project. There is an opportunity to upload your work in the second