Question: How much slack is there in task C? Your Answer: Your Answer Question 42 ( 4 points) If the crash costs for each task are
How much slack is there in task C? Your Answer: Your Answer Question 42 ( 4 points) If the crash costs for each task are A-200, B-150, C-250, D-275, and E-200, you would crash if you were asked to shorten the project by one day. Simply enter the capitalized letter for the task. You are given the following parameters for a project. There is an opportunity to upload your work in the second question. Question 39 (5 points) What is the critical path for the project? Use capital letters and no spaces. i.e. TFR or YG Question 40 (3 points) What is the duration of the project? Your