Question: how to calculate project duration Learning Activity 1 Based on the following table, a) draw the network for supposed processes A B 0 CRITICAL PATH
how to calculate project duration


Learning Activity 1 Based on the following table, a) draw the network for supposed processes A B 0 CRITICAL PATH D A B D nu 5 9 12 ES 0 EF 3 LS 3 LF 6 SLACK 3(6-3) LF-EF=SLACK 3 5 6 8 3(8-5) 9 8 12 3(12-9) HE AN AN 12 9 12 14 0(12-12) (14-14) Activity duration 14 = 3+2+4+3+2=14 DEO of 110ards b) calculate the project duration Activity Description initial market evaluations Predecessors Time (days) 3 I R&D B D scale up A, B C 2 4 3 obtaining legal permits launch to market E C, D 2