Question: Learning Activity 2 Based on the following table, a) Draw the network for supposed processes b) Calculate ES, EF, and the project duration Activity A

Learning Activity 2 Based on the following table,
Learning Activity 2 Based on the following table, a) Draw the network for supposed processes b) Calculate ES, EF, and the project duration Activity A Predecessors Time (days) 2 000 B 3 2 Description initial market evaluations R&D Supply of production materials and equipment scale up obtaining legal permits launch to market D 3 5 D, E F