Question: Learning Activity 1 Based on the following table, a) draw the network for supposed processes b) calculate the project duration Activity Description Predecessors Time (days)

Learning Activity 1 Based on the following table,
Learning Activity 1 Based on the following table, a) draw the network for supposed processes b) calculate the project duration Activity Description Predecessors Time (days) A initial market 3 evaluations B R&D 2 C A, B 4 D obtaining legal 3 permits E launch to market CD 2 scale up 2