Question: how to solve this question step by step. Calculate the number of workers that should have been available to process the July claims, and show

how to solve this question step by step.

Calculate the number of workers that should have been available to process the July claims, and show all work.

Standard time for processing per claim (simple claim)=36 minutes

Standard time for processing per claim (complex claim)=1.25 hours

Expected work hours per day 7.5 hours

Compensation cost per employee= $135 per day

Total working days=20

The number of July processed claims (simple)=3000

The number of July processed claims (complex)=960