Question: how would you solve this? Question 2 0 / 18.75 pts Job J is currently awaiting processing at WC202. J will require 7 hours of

how would you solve this? Question 2 0 / 18.75how would you solve this?

Question 2 0 / 18.75 pts Job J is currently awaiting processing at WC202. J will require 7 hours of processing time at WC202. After WC202, J will have process requirements of ... 10 hours at WC504 7 hours at WC603 15 hours at WC429 Standard move/queue time is calculated at 5 hours per work center. If Job J is due 59 hours from now, what is J's Critical Ratio? (Round to 2 decimal places) -1