Question: hy does a budget need to be closely integrated with the project schedule? estimates for costs are not made until later. budget constraints can require
hy does a budget need to be closely integrated with the project schedule?
estimates for costs are not made until later.
budget constraints can require schedule changes such as completing a task slowly to minimize financing costs.
the budget is a precedent for scheduling on the critical path.
costs are allocated to the period in which they occur.