Question: Why does a budget need to be closely integrated with the project schedule? the budget is a precedent for scheduling on the critical path. budget
Why does a budget need to be closely integrated with the project schedule?
the budget is a precedent for scheduling on the critical path.
budget constraints can require schedule changes such as completing a task slowly to minimize financing costs.
estimates for costs are not made until later.
costs are allocated to the period in which they occur.