Question: i . A consulting engineering firm is preparing a preliminary cost estimate for a 5 0 - MW advanced combined cycle natural gas - fired
i A consulting engineering firm is preparing a preliminary cost estimate for a MW advanced combined cycle natural gasfired power plant. The firm, which completed a similar project in with a total cost construction and equipment of $ million, wants to use a construction cost index to update the construction cost. If the construction cost was assumed to be of the total cost and the index value in was estimate the cost of construction for a similarsize plant in when the index is marks
ii If the powerplant stated is a government asset with annual benefits of million, is it economically justifiable over a year period? Discount rate is per year