Question: I am preparing a schedule, and it includes steel erection for a church. Our steel erection expert says the base rate for erection of this

I am preparing a schedule, and it includes steel erection for a church. Our steel erection expert says the base rate for erection of this type of structure is 8 tons per day and that a 15% time allowance is needed for weather delays, mostly delay due to winds higher than the limits of the crane operation. If the current drawings show a total of 73.5 tons of steel in the structure, what would be the number of workdays (rounded up to the next workday) to show for the duration of this work in the schedule, including the time allowance for weather?
A.7 workdays
B.9 workdays
C.10 workdays
D.11 workdays
E.12 workdays
F.14 workdays
G.16 workdays
 I am preparing a schedule, and it includes steel erection for

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!