Question: I. Analysis and Calculation [30 points) A network consists of the activities in the following list. Activity Duration Immediate Predecessors (days) 10 A B 8

I. Analysis and Calculation [30 points) A network
I. Analysis and Calculation [30 points) A network consists of the activities in the following list. Activity Duration Immediate Predecessors (days) 10 A B 8 --- C 3 A D 4 A E 5 B,C,D (1) Draw the AON network to represent this project. (2) Draw the AOA network to represent this project. (3) Calculate the ES, EF, LS, LF, and Slack for each activity. (4) What is the minimum project duration