Question: I ) Create a CPM network diagram ( AON - Activity on Node ) and determine the start and finish times along with the critical

I) Create a CPM network diagram (AON - Activity on Node) and determine the start and finish times along with the critical path of the project activities listed in Table I. You may work in teams of 2.
Table I: List of activities for a system derign project
\table[[Activity ID,Activity Description,Preceded by,Duration (days)],[A,Systems design,-,2],[B,Subsystem A design,A,1],[C,Subsystem B design,A,2],[D,Subsystem C design,A,1],[E,Program A,B,2],[F,Program B,C,10],[G,Program C,D,2],[H,Subsystem A test,E,1],[I,Subsystem B test,F,1],[J,Subsystem C test,G,1],[K,Integration,H,l,J,2],[L,Integration test,K,1]]
I ) Create a CPM network diagram ( AON - Activity

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!