Question: I DON'T KNOW WHAT I'M DOING WRONG ON THE QUESTIONS I GOT INCORRECT. PLEASE HELP. On February 1, 2016, Arrow Construction Company entered into a
I DON'T KNOW WHAT I'M DOING WRONG ON THE QUESTIONS I GOT INCORRECT. PLEASE HELP.
| On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,025,000. During 2016, costs of $2,010,000 were incurred, with estimated costs of $4,010,000 yet to be incurred. Billings of $2,512,000 were sent and cash collected was $2,260,000. |
| In 2017, costs incurred were $2,512,000 with remaining costs estimated to be $3,615,000. 2017 billings were $2,762,000, and $2,485,000 cash was collected. The project was completed in 2018 after additional costs of $3,810,000 were incurred. The companys fiscal year-end is December 31. This project does not qualify for revenue recognition over time. |
| Required: | |||||||||
| 1. | Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
| ||||||||
Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years Answer is complete but not entirely correct Gross profit (loss) Revenue Year recognize recognize 2,679,444X 669, 444X 2016 1,780,314X 2017 (781,444)X 3,565,242X (195,000) 2018 30 7.000 8,025,000 Total
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts













