Question: I need help finding the answer to this problem? From the project plan, we that a project has a total budgeted cost of $997,950 and
I need help finding the answer to this problem?
From the project plan, we that a project has a total budgeted cost of $997,950 and a project completion time of 15 weeks. At the moment, the project has been in a performing stage. At the end of week 8 , the project progress report shows that the project has consumed a total of $302,240, the project cumulative earned value is $341,068, and the project schedule performance index is 0.89. What is the estimated project cost at completion if the project continues at the cost performance index of 1.0 ? Use at least 4 decimals