Question: I need help finding the answer to this problem? cv= 41,011 and the other is SV From the project plan, we that a project has
I need help finding the answer to this problem?
cv= 41,011 and the other is SV
From the project plan, we that a project has a total budgeted cost of $674,531 and a project completion time of 17 weeks. At the moment, the project has been in a performing phase. At the end of week 7 , the project progress report shows that the project has consumed a total of $299,292, the project schedule variance is $41,011 ani the project schedule variance is $43,453. What is the estimated project cost at completion if the project continues at the cost performance index observed at the end of week 7 ? Use at least 4 decimals Step by Step Solution