Question: I need help finding what the question is asking for? Look at Project TX55: ES(D)=27,ES(E)=34,andES(F)=28 The duration of activities D,E, and F are 23,13 ,
I need help finding what the question is asking for?
Look at Project TX55: ES(D)=27,ES(E)=34,andES(F)=28 The duration of activities D,E, and F are 23,13 , and 13 days, respectively. The duration of activities G,H,K, and M are 27,17,21, and 16 days, respectively. Find the duration of activity C