Question: I need help with question c. please! The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel:



I need help with question c. please!
The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel: Activity ACUM Activity Time (days) Immediate Predecessor(s) onmou) a. Choose the correct network diagram for this project. Start - 0-0 Finish OOO OO b. Determine the critical path and project duration, The critical path is path A-C-D-E-G and the project duration is 21 days. (Enter your response as an integer.) c. Calculate the slack for each activity. (Enter your responses as integers.) Activity Slack (days) MOOO 000000Step by Step Solution