Question: Question 1 7 ( 6 points ) The following information is known about a project to upgrade a point - of - sale system at

Question 17(6 points)
The following information is known about a project to upgrade a point-of-sale system at the UNG bookstore:
\table[[Activity Activity Time (days),Immediate Predecessor(s),],[A,7,-],[B,2,A],[C,5,A],[D,3,B, C],[E,5,D],[F,3,E],[G,8,E]]
a. Determine the critical path and project duration.
b. Calculate the slack (in days) for each activity.
\table[[Activity,Slack (days)],[A,],[B,],[C,],[D,],[E,],[F,],[G,]]