Question: Question 1 7 ( 6 points ) The following information is known about a project to upgrade a point - of - sale system at
Question points
The following information is known about a project to upgrade a pointofsale system at the UNG bookstore:
tableActivity Activity Time daysImmediate PredecessorsABACADB CEDFEGE
a Determine the critical path and project duration.
b Calculate the slack in days for each activity.
tableActivitySlack daysABCDEFG