Question: I NEED THE SLACK ( days ) FOR THIS QUESTION!!!! The critical path is ABCEH, and project duration is 3 1 days. Here is the

I NEED THE SLACK (days) FOR THIS QUESTION!!!! The critical path is ABCEH, and project duration is 31 days. Here is the question:
Reliable Garage is completing production of the J2000 kit car. The following data are available for the project:
\table[[Activity,Activity Time (days),Immediate Predecessor(s)],[A,5,-],[B,7,A],[C,5,B],[D,7,C],[E,9,C],[F,3,C],[G,2,F],[H,5,D, E, G]]
a. Choose the correct network
diagram below for this project.