Question: A project has three paths. A - B - C has a length of 2 0 days. A - D - C has a length

A project has three paths. A-B-C has a length of 20 days. A-D-C has a length of 30 days. Finally, A-E-C has a length of 25 days. Which one of the following statements is
true?
Question content area bottom
Part 1
A.
A-D-C has the most slack.
B.
The expected duration of this project is 20+30+25=75 days.
C.
A-D-C is the critical path.
D.
The expected duration of this project is 20 days.